How we prepare a stainless steel work platform for installation

Before dispatch, we assemble every multi-section stainless steel work platform in full in our workshop. We check how the sections fit together and make any adjustments in-house. This keeps installation on site predictable and your plant project on schedule.

Multi-section stainless steel work platform with stairs and guardrails during workshop assembly

Trial assembly of the frame sections

We bolt the frame sections together during trial assembly. At each joint, we check that the bolt holes line up, the connection plates sit flush and the sections meet at the specified height. If a joint needs adjusting, we do it while the platform is assembled.

Two colleagues working on the platform frame during trial assembly
Trial assembly in the workshop.
Bolted connection plates joining two work platform frame sections
Two frame sections bolted together at the joint.
Deck plate and formed edge on a stainless steel work platform

We weld the deck plates in the workshop

We weld the deck plates to their respective frames in our workshop. The frame sections can still be unbolted. The decks arrive on site already fitted to their frames, reducing the amount of welding needed there.

Do the stairs fit? Does the gate close?

During trial assembly, we fit stairs, guardrails and safety gates at their designated connection points. We check the transition from the stairs to the deck, align the guardrails and test each gate. If it rubs or the latch does not engage properly, we adjust it in the workshop.

Stair stringer bolted to the platform frame
Stair connection at the platform frame.
Bolted guardrail connection at the platform frame
Guardrail connection at the frame.
Closed safety gate at the stair access to a stainless steel platform
Safety gate at the top of the stairs.

100%

of platform connections checked during trial assembly.
We recheck each connection after any adjustment.

We dismantle the platform for transport

For transport, we remove the guardrails, gates and stairs and unbolt the frame sections. The deck plates stay on their frames. We label and pack the assemblies so the installation crew can identify each section and reassemble the platform at the checked connection points.

Dismantled frame sections and stairs separated by timber spacers for transport
Frame sections and stairs ready for dispatch.

Every work platform is built to fit

Equipment, pipework and existing access points determine the dimensions and connections of each platform. We design the platform and divide it into sections accordingly. Trial assembly confirms the fit before dispatch, avoiding unplanned adjustments on site that can hold up other trades.